Knowl Park House – Build update February 2024

Panoramic shot of the exterior of Knowl Park House

Here’s the latest from our dementia day care build in Mirfield.

What’s been happening?

We start with the base for the sprinkler tank which is now complete.

Contractors are working on the terracotta rainscreen system around the building and the scaffolding around the feature roof and the main entrance has now been removed.

External facade of Knowl Park House.
External view of Knowl Park House with roof light installation.

The final roof lights have now been installed along with the screeding of the internal floors which is also complete. The contractors have progressed work in the courtyard, with work continuing on the block paving and edges.

External view of Knowl Park House.

Next up…

Contractors are about to start work on the ceilings and will be continuing the plastering and painting within the new building.

Internal shot of Knowl Park House build.

The contractors will also be completing the hard landscaping that is currently taking place within the courtyard.